Project Title | Construction works for rehabilitation and upgrading of the Railway Station – Skopje in line with the requirements addressed in the assessment |
Main Objectives of the Project | The overall objective of the operation is to improve the overall quality of services for the all the passengers, to increase technical standards, capacity of the railway station, transport safety and development of railway infrastructure, quality of the railway station and overall interest for travelling by train by rehabilitation of the railway station. |
Project Outputs/Activities | Construction works for rehabilitation and upgrading of the Railway Station Skopje in line with the requirements address in the assessment |
Start Date | 15th May 2014 |
End Date | 01th October 2015 |
Project type | EuropeAid133160/D/WKS/MK
Works contract number 11-14278/1 |
Project Budget | 1.547,888.22 € |
Contractor’s name | INKOM inzenering DOOEL in consortium with BONOR inzenering DOOEL and GLOBOCKI DOOEL |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |
Project Title | Supervision services of the works and supply contracts for rehabilitation and upgrading of the Railway Station – Skopje in line with the requirements addressed in the assessment |
Main Objectives of the Project | The overall objective of the operation is to improve the overall quality of services for the all the passengers, to increase technical standards, capacity of the railway station, transport safety and development of railway infrastructure, quality of the railway station and overall interest for travelling by train by rehabilitation of the railway station. |
Project Outputs/Activities | Supervision of the Construction works for rehabilitation and upgrading of the Railway Station Skopje in line with the requirements address in the assessment |
Start Date | 28th April 2014 |
End Date | 01th August 2017 |
Project type | EuropeAid/132633/C/SER/multi
Service contract number 11-11799/1 |
Project Budget | 143.604,15 € |
Contractor’s name | ARS PROGETTI SPA AMBIENTE RISORSE E SVILUPO |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |
Project Title | Rehabilitation and upgrading of the Railway Station Skopje according to EU best practices(Preparation of Tender dossier including Detailed Design with technical specification for works contract and preparation of ToR for Fwc for supervision |
Main Objectives of the Project | The specific objective of this assignment is preparation of high quality technical documentation as follows:
Detailed Design for the Project “Rehabilitation and upgrading of the Railway Station – Skopje according to the EU best practices”, Full Tender Dossier for Works Contract and Specific Terms of Reference for the Framework Contract for Supervision services for the Works Contract. |
Project Outputs/Activities | Detailed Design approved by the Contracting Authority, after prior consultation by the Steering Committee;
Full Tender Dossier for Works Contract prepared, according to the latest PRAG procurement rules and procedures and to the FIDIC red book for implementing the works (conditions of the contract and approved by the Contracting Authority, after prior consultation by the Steering Committee); Terms of Reference prepared, including Indicative budget for the Framework Contract for the Supervision services of the works approved by the Contracting Authority, after prior consultation by the Steering Committee. |
Start Date | 22th August 2011 |
End Date | 05th September 2012 |
Project type | EuropeAid/127054/C/SER/multi
Service contract number 09-25822/1 |
Project Budget | 109.665,00 € |
Contractor’s name | GRONTMIJ/CARL BRO A/S |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |
Project Title | Supply and installation of electrical and other networks and equipment for rehabilitation and upgrading the railway station Skopje in line with the requirements addressed in the assessment – LOT 1 |
Main Objectives of the Project | The overall objective of the operation is to improve the overall quality of services for the all the passengers, to increase technical standards, capacity of the railway station, transport safety and development of railway infrastructure, quality of the railway station and overall interest for travelling by train by rehabilitation of the railway station. |
Project Outputs/Activities | Supply, delivery, unloading, installation, testing, putting into operation, training and warranty services of equipment for rehabilitation and upgrading of the railway station Skopje in line with the requirements addressed in the assessment and as prescribed in the technical specification |
Start Date | 02th June 2014 |
End Date | 31th December 2015 |
Project type | EuropeAid134099/D/SUP/MK
Supply contract number 11-8240/1 |
Project Budget | 262.908,71 € |
Contractor’s name | KERNEL MAKEDONIA DOO export import Skopje in consortium with VISTA Group DOOEL |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |
Project Title | Supply and installation of electrical and other networks and equipment for rehabilitation and upgrading the railway station Skopje in line with the requirements addressed in the assessment – LOT 2 |
Main Objectives of the Project | The overall objective of the operation is to improve the overall quality of services for the all the passengers, to increase technical standards, capacity of the railway station, transport safety and development of railway infrastructure, quality of the railway station and overall interest for travelling by train by rehabilitation of the railway station. |
Project Outputs/Activities | Supply, delivery, unloading, installation, testing, putting into operation, training, as prescribed in the technical specification: CCTV, Passenger Information system, Management building system and CAS |
Start Date | 27th May 2016 |
End Date | 01th July 2017 |
Project type | EuropeAid134099/IH/SUP/MK
Supply contract number 12-1567/1 |
Project Budget | 449.830,00 € |
Contractor’s name | Siemens doo Beograd |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |
Project Title | Rehabilitation, upgrading and reconstruction of Railway Stations along Pan European Corridor X including branch XD, according to the EU best practices – LOT1 |
Main Objectives of the Project | The overall objective of this Operation is improving the overall quality of the services for the passengers and cargo increasing the technical standards and capacity of the railway stations and overall interest in travelling and shipping by train. |
Project Outputs/Activities | Rehabilitation of the railway station stations, Veles, Cashka and Bogomila |
Start Date | 27th May 2015 |
End Date | 18th October 2016 |
Project type | EuropeAid135077/D/WKS/MK
Works contract number 12-2612/1 |
Project Budget | 588.147,5822 € |
Contractor’s name | VIA DOO export import Vevcani in consortium with ILINDEN AD Struga |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |
Project Title | Rehabilitation, upgrading and reconstruction of Railway Stations along Pan European Corridor X including branch XD, according to the EU best practices – LOT2 |
Main Objectives of the Project | The overall objective of this Operation is improving the overall quality of the services for the passengers and cargo increasing the technical standards and capacity of the railway stations and overall interest in travelling and shipping by train. |
Project Outputs/Activities | Rehabilitation of the railway station stations, Prilep and Bitola |
Start Date | 27th May 2015 |
End Date | 18th October 2016 |
Project type | EuropeAid135077/D/WKS/MK
Works contract number 12-2614/1 |
Project Budget | 473.625,03 € |
Contractor’s name | VIA DOO export import Vevcani in consortium with ILINDEN AD Struga |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |
Project Title | Rehabilitation, upgrading and reconstruction of Railway Stations along Pan European Corridor X including branch XD, according to the EU best practices – LOT3 |
Main Objectives of the Project | The overall objective of this Operation is improving the overall quality of the services for the passengers and cargo increasing the technical standards and capacity of the railway stations and overall interest in travelling and shipping by train. |
Project Outputs/Activities | Rehabilitation of the railway station stations Demir Kapija, Gradsko, Tabanovce and Negotino |
Start Date | 27th May 2015 |
End Date | 18th October 2016 |
Project type | EuropeAid135077/D/WKS/MK
Works contract number 12-2615/1 |
Project Budget | 588.574,71 € |
Contractor’s name | VIA DOO export import Vevcani in consortium with ILINDEN AD Struga |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |
Project Title | Rehabilitation, upgrading and reconstruction of Railway Stations along Pan European Corridor X including branch XD, according to the EU best practices – LOT4 |
Main Objectives of the Project | The overall objective of this Operation is improving the overall quality of the services for the passengers and cargo increasing the technical standards and capacity of the railway stations and overall interest in travelling and shipping by train. |
Project Outputs/Activities | Rehabilitation of the railway station station Gevgelija |
Start Date | 20th May 2015 |
End Date | 18th July2017 |
Project type | EuropeAid135077/D/WKS/MK
Works contract number 12-2616/1 |
Project Budget | 302.006,23 € |
Contractor’s name | Konstruktor Renata I dr ltd export-import Skopje |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |
Project Title | Supervision of the Rehabilitation, upgrading and reconstruction of the railway stations along Pan-European Corridor X including branch Xd according to the EU best practices |
Main Objectives of the Project | The overall objective of this Operation is improving the overall quality of the services for the passengers and cargo increasing the technical standards and capacity of the railway stations and overall interest in travelling and shipping by train. |
Project Outputs/Activities | Supervising activities on implementation of the works contract |
Start Date | 29th April 2015 |
End Date | 28th April 2017 |
Project type | EuropeAid132633/C/Ser/multi
Service contract number 12-2218/1 |
Project Budget | 243.600,00 € |
Contractor’s name | COWI Belgium sprl |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |
Project Title | Rehabilitation, upgrading and reconstruction of Railway Stations along Pan European Corridor X including branch XD, according to the EU best practices |
Main Objectives of the Project | The overall objective of this Operation is improving the overall quality of the services for the passengers and cargo increasing the technical standards and capacity of the railway stations and overall interest in travelling and shipping by train. |
Project Outputs/Activities | Preparation of assessment study of the current situation of the prioritised Railway Stations
|
Start Date | 23th August2011 |
End Date | 01th October 2013 |
Project type | EuropeAid127054/C/Ser/multi
Service contract number 09-26559/1 |
Project Budget | 174.147,00 € |
Contractor’s name | ALA net Global |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |
Project Title | Preparation of project studies and design documentation for the railway sections along Corridor X including branch Xd |
Main Objectives of the Project | The overall objective of the project is the improvement of the railway links along the international Corridor X including branch Xd |
Project Outputs/Activities | Preparation of project studies and design documentation for three sections along the international Corridor X including branch Xd – section Kumanovo-Deljadrvoce, Dracevo-Veles and Bitola-Kremenica |
Start Date | 05th July 2012 |
End Date | 05th December 2014 |
Project type | EuropeAid130167/D/SER/MK
Service contract number 09-21997/1 |
Project Budget | 1.455.050 € |
Contractor’s name | ILF and consortium partners |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |
Project Title | Preparation of studies for development of strategic multimodal transport nodes |
Main Objectives of the Project | The overall objective of the project is increasing the mobility of people and goods following the single market objectives and the principles of sustainable mobility and sustainable development. |
Project Outputs/Activities | Activities
Sectoral Feasibility Phase Diagnostic study Assessment of trade flows against existing procedures on external trade and export promotion Analysis of trade balance for most traded goods and consequences for design capacity of potential multimodal transport nodes Selection of potential locations Traffic analysis and forecast Preliminary technical design and estimation of capital costs Preliminary assessment of environmental impacts Assessment of institutional requirements Definition of methodology for multi criteria (MCA), execution of MCA and formulation of conclusions and recommendations Presentation of recommendations of the Sectoral Feasibility Study & Revision of Sectoral Feasibility Study for final approval by the Contracting Authority upon recommendations of the Steering Committee Support the Operating Structure in the public information process Activities Cost-Benefit Analysis Phase Elaboration of capital costs estimation Preparation of Cost Benefit Analysis Revision of Cost Benefit Analysis for approval and presentation of outputs |
Start Date | 05th April 2012 |
End Date | 05th Fevruary2014 |
Project type | EuropeAid130030/D/SER/MK
Service contract number 09-9487/1 |
Project Budget | 1.100.00 € |
Contractor’s name | ECORYS Nederland B.V |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |
Project Title | “Preparation of Detailed design and tender documentation for construction works and supervision for the new railway section Kriva Palanka-Border with Republic of Bulgaria as part of Corridor VIII.” |
Main Objectives of the Project | The overall objective of this project is improvement of the rail infrastructure along the trans-European transport network, by establishing an operational continuity of railway corridor VIII, Albania (Port of Durres) – Macedonia (Kumanovo – Beljakovce – Kriva Palanka – state border) – Bulgaria (Port of Burgas), in order to meet the required EU standards. |
Project Outputs/Activities | Task 1: Update Feasibility Analyses.
Task 2: Update existing ESIA. Task 3: Prepare Procurement Strategy and Preliminary Design Report. Task 4: Prepare Main Designs for permanent way, Preliminary and Main Designs for several civil engineering structures, stations and electrification for Section 3. Task 5: Prepare Main Designs for cross-border tunnel “Deve Bair” and belonging part of permanent way located on the territory of the Republic of Bulgaria. Task 6: Prepare Preliminary Designs for signalling, ETCS-1 and telecommunication (CTC) for Section 3. Task 7: Prepare Main Design(s) for electrification of Sections 1 and 2. Task 8: Prepare Preliminary Design for GSM-R for all 3 Sections (from Kumanovo – Border with Bulgaria). Task 9: Prepare Technical parts of Tender Documents for Works Contracts (Volumes 3, 4 and 5 according to PRAG and FIDIC conditions of contracts) for Sections 1, 2 and 3 as applicable. Task 10: Design and conduct (on-the-job) trainings / workshops for preparation of BoQ and breakdowns of lump-sum prices. |
Start Date | 14th December 2015 |
End Date | 01th October2017 |
Project type | EuropeAid136050/IH/SER/MK
Service contract number 12-8859/1 |
Project Budget | 3.395.000,00 € |
Contractor’s name | IDOM with its consortium parties |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |
Project Title | “Preparation of project documentation (FS, PD, CBA, EIA and DD) and necessary documentation for tender dossiers for works and supervision of the works for reconstruction and rehabilitation for the Railway Section Skopje (Gjorce Petrov)-Kicevo as part of Corridor VIII. |
Main Objectives of the Project | This project will improve the railway infrastructure; will establish operational continuity of the rail Pan-European Corridor VIII thus will increase the socio-economic development of the region of Southeast Europe, by improving the connectivity of the transportation infrastructure. |
Project Outputs/Activities | Preparation of project documentation for future construction of the new railway section Kicevo-Border with Republic of Albania as part of Pan European Corridor VIII with a length of about 62.6 km. The consultants will prepared Detailed design for new one-way electrified railway line, from the existing railway station in Kicevo to the Border with Republic of Albania, according to the existing feasibility study, preliminary design and EIA studies, according to the EU best practices and also will prepared complete tender dossier for construction works and supervision of the construction works. |
Start Date | 15th October 2014 |
End Date | 15th August 2018 |
Project type | EuropeAid133591/D/SER/MK
Service contract number 11-28412/1 |
Project Budget | 7.752.425,00 € |
Contractor’s name | TYPSA with its consortium parties |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |
Project Title | Construction works for renewal with Reconstruction of the Railway Section Bitola-Kremenica, as part of branch XD of Corridor X” |
Main Objectives of the Project | The overall objective of the project of which this contract will be a part is as follows:
Rehabilitation of railway link along the TEN-T- Corridor X, branch Xd, increasing its capacity for better cohesion with the EU Member States and neighbouring countries, and promoting sustainable development through minimizing the adverse effects of transport on the environment and through improving transport safety. |
Project Outputs/Activities | Reconstruction of the non-electrified single-track railway section Bitola–Kremenica of a length of approx. 17 km, as part of Xd of corridor X in accordance with FIDIC ‘Conditions of contract for building and engineering works designed by the employer’, first edition1999 — FIDIC ‘Red Book’. |
Start Date | 22th December 2014 |
End Date | 01th November 2018 |
Project type | EuropeAid135451/IH/WKS/MK
Works contract number 11-44053/1 |
Project Budget | 18.995.945 € |
Contractor’s name | VODSTROY 98 AD and its consortium parties |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |
Project Title | Supervision for renewal with reconstruction of the railway section Bitola – Kremenica, as part of Xd of Corridor X |
Main Objectives of the Project | The overall objective of the project of which this contract will be a part is as follows:
Rehabilitation of railway link along the TEN-T- Corridor X, branch Xd, increasing its capacity for better cohesion with the EU Member States and neighbouring countries, and promoting sustainable development through minimizing the adverse effects of transport on the environment and through improving transport safety. |
Project Outputs/Activities | Supervision services for reconstruction of the non-electrified single-track railway section Bitola–Kremenica of a length of approx. 17 km, as part of Xd of corridor X in accordance with FIDIC ‘Conditions of contract for building and engineering works designed by the employer’, first edition1999 — FIDIC ‘Red Book’. |
Start Date | 14th January 2015 |
End Date | 01th December 2018 |
Project type | EuropeAid135413/IH/SER/MK
Service contract number 11-45133/1 |
Project Budget | 900.100,00 € |
Contractor’s name | |
Beneficiary | Ministry of transport and communications |
Responsible Implementing Department within MoEPP as end beneficiary | Department for European Union – IPA Monitoring Unit |
End Beneficiary (other than MoEPP such as municipality and PUC) | PE Macedonian Railways Infrastructure |
Project Related Links (Websites) | www.oprd.gov.mk |